Relicensing MAJOR RELICENSING MILESTONES. FERC License Application Processing The FERC will review the FLA for adequacy under the FPA requirements and either accept of reject it. It is not unusual for the Commission to issue Additional Information Requests (AIRs) to obtain the information necessary for the Commission staff to prepare the FERC Draft Environmental Assessment. The FERC DEA is in the same format and contains roughly the same information as the Applicant’s DEA, but is the result of independent FERC Staff review, and may not present the same conclusions as the Applicant’s DEA. The FERC DEA review period is 30 days. When the additional information is acceptable, the FERC issues a “Ready for Environmental Assessment” Notice, and requests Final Terms and Conditions from applicable resource agencies. If the Applicant disagree with any of the Terms and Conditions, FERC may implement formal Dispute Resolution.