RELICENSING SCHEDULE

The FERC relicensing schedule requirements are shown in the detailed schedule diagrams which depict the FERC process. The Blue Lake Project relicensing schedule milestones and dates are shown in the flow diagram available in the website.

Generally, the timeline for relicensing is as follows:

Activity or Milestone
Timeframe
Final Notice of Intent, Information Files November, 2002
Initial Consultation Document and Meetings November, December, 2002
Study Planning and Field Studies 2002-2007
Scoping Process September-October, 2003
Submit Draft License Application March, 2005 (Approximate Date)
Submit Final License Application March, 2006
FERC Activity on License Application March, 2006-2008
FERC Order Issuing New License March, 2008


.