General Information
Phone Numbers
(907)747-1804
Fax: (907)747-3158
Emergencies: Dial 911
Location
100 Lincoln Street
Sitka,
AK
99835

Hours
Monday - Friday
8:00am - 5:00pm

Engineering

Welcome to the Engineering Page.

Engineering is here to manage the planning, design and construction of roads, utilities, buildings and harbor projects:

  • Plan, organize and manage implementation of capital projects within the City and Borough of Sitka.
  • Manage and implement Water, Wastewater, Stormwater, Roads & Harbor Master Plans.
  • Review plans, inspect and approve private subdivision development.
  • Issue permits for new water & sewer services, driveways, and encroachments.
  • Review and approve traffic control plans for work within municipal right-of-way.
  • Coordinate Public Works GIS database and mapping.
  • Pursue funding for various Capital Improvement Projects (CIPs).
  • Prepare grant and loan applications for Alaska Department of Environmental Conservation, Alaska Energy Authority, Legislative Requests, State of Alaska Harbor Matching Grant, etc.
  • Respond to public inquiries/concerns regarding drainage and right-of-way issues.
  • Support PW Building Division with grading, retaining wall, and geotechnical report review and inspections.
  • General engineering support for other City departments and PW divisions.


Current Public Works Projects Progress Report

This report outlines all active projects the Public Works Department is currently working on.  Click here for   3 June - 2022 Public Works Assembly Update.pdf 

 

 

For projects currently out to bid, please visit our Bids and RFP page.

Questions on any current or past bids can be asked at publicworks@cityofsitka.org or by calling the Public Works department at 907-747-1804

 

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

 

New Sitka Seaplane Base (SPB)


Project Description: 

The City and Borough of Sitka (CBS) is proposing to construct a new seaplane base (SPB) on Japonski Island to replace the exisiting SPB, which is deteriorating and in poor condition.  A masterplan for a new SPB was completed in 2002. Additional siting studies were completed in 2012 and updated in 2016, to identify the best location for the new facility. Tha Japonski Island site was identified as the preferred site.  CBS has now received Federal Aviation Administration (FAA) funding for further planning and environmental studies on the proposed new SPB.  Environmental review, under the National Environmental Policy Act (NEPA), is required before the FAA can approve funding for the airport land acquistion, design, permitting and construction of the facility. FAA typically pays for 93.75% of the project costs.

 

For more information about Sitka Seaplane Base - click here

 

 

Critical Secondary Water Supply

Project Description: 

CBS needs a reliable, safe source of drinking water to serve to the public for when the Blue Lake penstock is down for maintenance, or for when there is high turbidity in the Blue Lake raw water. This project will design and construct a water intake in Sawmill Creek and a filtration plant at Gary Paxton Industrial Park to meet these needs.

 

 

Frequently Asked Questions (FAQ) Project Overview:

The following is the link of the overall project information that was presented to the assembly and the public.

 

FAQ Critical Secondary Water

 

Documents:

Cost Estimate Update, September 2019

Sawmill Creek intake Memo, July 2019

Backwash Disposal Memo, July 2019

Dedicated Water Supply Report, January 2018

Filtration Evaluation for Critical Secondary Water Source, April 2019

Summary of Design Considerations

ADEC Compliance Order by Consent Determination, May 2019

Project Cost Estimate, September 2019

CSW Membrane Award Recommendation, November 2019

Preliminary Drawings, January 2020

Basis of Design Report, January 2020

 

 

Airport Terminal Improvements

Project Description: 

The Airport Terminal Improvement Project is intended to remedy some of the existing critical problems identified in the Airport Terminal Master Plan 2008-2011, including working conditions in the baggage make-up area and TSA baggage screening area, as well as problems with congested passenger queuing, screening, baggage, fish boxes, waiting areas and passenger flow. CBS accepted a TSA design grant in the amount of $158,569.25 to design specific improvements to the TSA Baggage Screening Area. Other areas impacted by these design changes are ineligible for the TSA design funding. The Assembly approved moving forward to the 65% Schematic Design Milestone for the preferred concept plan that was presented in the Assembly work-session August 8, 2017.  Passenger Facility Charges (PFC) were applied for and approved by ADOT and FAA. Collection of the PFCs began May 1, 2018. The total anticipated revenue collection over the 20-year period of collection is $6,840,000.00, which will finance the $4,025,000 revenue bond along with its fees and debt service.

 

The estimated cost for the project as identified is approximately $15 Million.  The current funding plan outlines the following components:

 

  • Passenger Facility Charge Revenue                           $4,025,000   Bond Secured
  • TSA OTA Grant                                                                   $158,569            Secured
  • TSA Funding                                                                     $3,397,500        Unsecured
  • Eligible AIP Grant Request                                            $10,283,954       Unsecured

Documents:



Assembly Memo & Concept Plan, August 2017

Assembly Work Session, August 8, 2017

2011.Sitka Airport Master Plan.Final.pdf 

 

 

Sitka Police Station Study

Project Description: 

The Sitka Police Station Planning Study, completed August 2019, is an initial planning and programming study that takes a preliminary look at the spatial needs for a new police station and jail, based on the Sitka Police Station’s existing operations and the standard sizes of the spaces required to perform those operational activities.  The study is intended to provide a comprehensive go-to document that captures the efforts, investigations and known project information to-date.  Design of the facility will be implemented at a future time where its final size and amenities will be determined along with its location, based on future funding and the other ‘next steps’ listed in the attached study.

 

Documents:

Final Police Station Study

 

 

Contractor Resources - Click Here